April 2024 – Project Update

Click here to view the slides from the April 2024 NSBC Meeting Presentation.

Demoing sidewalk, excavating for hydrant line courtyard adjacent to D Building East side
Backfilling at stripped sidewalks in the courtyard
Countertop and E3 prepping epoxy sink for installation
F Auditorium West wall elevation drywall installation